Raw material homogenization production plan in multiple quarries-slope stability assessment: Cement raw material clay pit sample


Karakus D.

JOURNAL OF MINING SCIENCE, cilt.48, sa.1, ss.154-166, 2012 (SCI-Expanded) identifier identifier

  • Yayın Türü: Makale / Tam Makale
  • Cilt numarası: 48 Sayı: 1
  • Basım Tarihi: 2012
  • Doi Numarası: 10.1134/s1062739148010170
  • Dergi Adı: JOURNAL OF MINING SCIENCE
  • Derginin Tarandığı İndeksler: Science Citation Index Expanded (SCI-EXPANDED), Scopus
  • Sayfa Sayıları: ss.154-166
  • Anahtar Kelimeler: cement raw materials, mine planning, production scheduling, slope stability
  • Dokuz Eylül Üniversitesi Adresli: Evet

Özet

Up-to-date solution algorithms, which are used to determine optimum production sequences and ultimate pit limits are discussed. These private solutions for quarries might be inadequate for different mining areas. Optimization solutions that are offered for quarries in raw material preparation process within constraints, which are determined by mixing raw material that were produced from different quarries such as cement production, fall short, instead these are replaced by trial and error methods that are made for main constraints. In this study, production sequence homogenization study for limestone that belongs to a cement factory and clinker production from two clay pits were presented, slope stability assessment was also made. As a result of these studies, a planning process based on production amounts, distances, chemical content of clinker and slope safety constraints was developed.